INSTALLATION PTH 60/8

  • Drill a hole through the insulation board with the right diameter.
  • Insert the anchor into the hole with the anchor plate flush in contact with the insulation material. Slightly hammer the anchor plate surface in order to push it between 0 and 2mm under the insulation material surface.
  • If the anchor setting is difficult, it probably means that the used drill bit is worn (the drilled diameter is too small or the dust remains inside the hole). It is then necessary to use a new drill bit or better clean the hole.
  • Hammer the head of the steel nail until it becomes flush with the anchor plate.
  • An 800g hammer is recommended to perform an optimal installation.
  • Within 6 weeks the anchors should be covered by the other ETICS components (for UV protection).
  • Installation must be done at a temperature >0°C.